Maintenance and Blackout Schedules

Import · Jul 07, 2020 · article

I have tested Conflict for these schedules which are Blackout and Maintenance

  • Only Maintenance Schedule is Active on: Monday, Tuesday, and Wednesday
Planned Start Date Planned End Date Results
Friday Monday Maintenance Schedule Conflict
Monday Wednesday No Conflict
Monday Friday Maintenance Schedule Conflict
  • Only Blackout Schedule is Active on: Wednesday, Thursday
Planned Start Date Planned End Date Results
Monday Wednesday Blackout Schedule Conflict
Wednesday Thursday Blackout Schedule Conflict
Wednesday Friday Blackout Schedule Conflict
Tuesday On Same Tuesday No Conflict
Friday On Same Friday No Conflict
  • Both Maintenance and Blackout Schedule are Active
  • Maintenance Schedule: Monday, Tuesday, Wednesday
  • Blackout Schedule: Wednesday, Thursday
Planned Start Date Planned End Date Results
Monday Wednesday Blackout Schedule Conflict
Friday Tuesday Maintenance Schedule Conflict
Tuesday Friday Blackout Schedule Conflict
Maintenance Schedule Conflict
Friday Friday Blackout Schedule Conflict
Maintenance Schedule Conflict
Friday On Same Friday Maintenance Schedule Conflict
Monday Tuesday No Conflict
Friday Wednesday Blackout Schedule Conflict
Maintenance Schedule Conflict
Thursday Thursday Blackout Schedule Conflict
Maintenance Schedule Conflict
Tuesday Wednesday Blackout Schedule Conflict
Wednesday Wednesday Blackout Schedule Conflict
Monday Friday Maintenance Schedule Conflict

*Note:

If Change is planned outside Maintenance Window-->Maintenance Conflict

If Change is planned in Blackout than -->Blackout Conflict

If Change is planned to start in Maintenance Window but it ends outside Maintenance Window in which some are Blackout days--> Both the conflicts

Documented by

-Nitesh

Please mark helpful if someone really feels its helpful.