Expected Percent Complete

Import · Feb 25, 2021 · article

Hey Everyone

I have developed a functionality to include project's Expected Percent Complete on project which helps PMs to calculate the variance of Percent Complete.

This can be used on any version since this is completely custom and you will not have any problems during upgrades as well.

This can be done for single project through related link or multiple projects at once through list button.

The field Expected Percent Complete is = (No of task's planned end date is on or before today/total no. of tasks)*100

Project Form

image

Related Link

image

After clicking link

image

Project List view button (You can also apply filters to the list and it will calculate only to those projects)

image

after clicking button

image

after the update is complete

image

Hope this article is helpful to you guys.

Thanks and Regards

M. Ashwath Kumar Reddy